Existing MS Excel headers
Task Name, duration, start and end date
Existing MS Project headers
Task Name, duration, start, finish, predecessors, resource names, mileston, % complete
Steps taken to import Excel data
In MS Project – File, Open, and selected Excel Workbook (*.xlsx), and clicked open
Project Import Wizard, Next, New map, merge data into active project, Tasks
Source worksheet name comes up as (none)
Other option is the name of my tab, which I select.